Groundbreaking ~ September 16, 2024
Groundbreaking ~ September 16, 2024
Groundbreaking ~ September 16, 2024
December 5, 2024 ~ Surveying in Progress
February 5, 2025 - First load of gravel
Feb. 24, 2025 ~ A little too much rain.
March 13, 2025 ~ Gravel Driveway
Mar. 26, 2025 ~ Clarifier Holes (17' D x 30' diameter)
Mar. 28, 2025 ~ Wastewater Pipes being laid into place
Mar. 28, 2025 ~ Wastewater Pipes being laid into place
March 29, 2025 ~ All pipes laid and covered.
March 31, 2025 ~ Holding Pond Outfall
April 2, 2025 ~ Crane preparing to bring in Rebar
April 8, 2025 ~ Wastewater Treatment Plant Area View
April 10, 2025 ~ Creating space for Digester
April 14, 2025 ~ Looking at the Clarifiers
April 16, 2025 ~ Stone going into the clarifiers
April 23, 2025 ~ Crane transporting reinforced bars
April 28, 2025 ~ Crane moved all rebar
April 29, 2025 ~ Working on the Chlorine Contact Chamber
April 29, 2025 ~ The Carousel is being dug
April 30, 2025 ~ Concrete for Clarifier
May 19, 2025 ~ Placement of Clarifier
May 19, 2025 ~ Reinforced Steel being laid
May 19, 2025 ~ Reinforced Steel being laid
May 19, 2025 ~ Reinforced Steel in Aerobic Digester
May 21, 2025 ~ Concrete for both Clarifiers
May 21, 2025 ~ Concrete for both Clarifiers
May 21, 2025 ~ Concrete for both Clarifiers
May 22, 2025 ~ Fill and Compaction
May 28, 2025 ~ Start of Rebar for Carousel
May 28, 2025 ~ Post Aeration received concrete
May 28, 2025 ~ Bio-solids received base concrete
May 28, 2025 ~ Two Clarifiers are ready for form walls
June 5, 2025 ~ Carousel is almost ready for concrete